Markets 28 August 2026 13 min read

82% of America's Large Transformers Are Imported: Inside the 26 August 2026 Bulk-Power System Emergency Order — and Why a Ban Is Not a Tariff

A 26 August emergency order bans some foreign-made grid equipment. The Department of Commerce says 82% of US large power transformers are imported. The mechanism.

82% of America's Large Transformers Are Imported: Inside the 26 August 2026 Bulk-Power System Emergency Order — and Why a Ban Is Not a Tariff
Photo: public domain, via Wikimedia Commons.

82% of America's Large Transformers Are Imported: Inside the 26 August 2026 Bulk-Power System Emergency Order — and Why a Ban Is Not a Tariff

On Wednesday 26 August 2026 the White House issued an executive order titled "Declaring a National Emergency to Secure the United States Bulk-Power System", generally prohibiting the acquisition, importation, transfer or installation of foreign-produced grid equipment in which a "Covered Foreign Entity" holds an interest. It names no country, sets no rate, and specifies no dollar threshold — the Department of Energy has 120 days to write the rules that decide what is actually banned. The number that determines how much this matters is not in the order at all: the Department of Commerce estimated that 82% of the large power transformers used in the United States are imported, and DOE's own supply-chain work says the domestic alternative cannot make the steel its cores are wound from.

Key takeaways
  • It is a prohibition, not a tariff. The order rests on the International Emergency Economic Powers Act, the National Emergencies Act and 3 U.S.C. 301 — and prohibits transactions rather than taxing them. A tariff clears at a higher price. A ban clears through a queue.
  • Same statute the Supreme Court narrowed in February, used the other way. The 20 February 2026 ruling held that IEEPA confers no tariff power because taxing is an Article I power. Blocking transactions has been IEEPA's core function since 1977 and was untouched.
  • The scope does not exist yet. "Covered Foreign Entity" is defined by conduct and sanctions status, not by country. DOE implementing rules are due within 120 days — 24 December 2026; Federal Acquisition Regulation recommendations within 180 days, 22 February 2027.
  • Import dependence is the multiplier. Commerce's 2019 count: 137 large power transformers (18%) domestic, 617 (82%) imported. Domestic capacity utilisation ~40%; maximum domestic output ~343 units a year.
  • The constraint sits one layer below the transformer. Grain-oriented electrical steel and copper conductor are each roughly 25% of a transformer's production cost, about 80% of that steel was imported, and the highest grade is made by a single manufacturer in Japan and not made in America at all.
  • It landed as a policy event, not a price event. That is the correct reading while the covered set is undefined — and the reason to watch the December rulemaking rather than the signing.
  • The slow channel is the electricity line of CPI. It rose 4.20% in the year to July 2026 against 3.36% headline. Capex becomes rate base becomes retail price becomes an inflation print, over regulatory quarters.
  • See how the rate, growth and risk factors are scoring the eight majors right now on the live meter.

What the order does, and what it conspicuously leaves blank

The operative sentence prohibits "any acquisition, importation, transfer, or installation of any foreign-produced bulk-power system electric equipment" where a Covered Foreign Entity has an interest and where the transaction was initiated after the date of the order. Three features of the drafting matter more than the headline.

The first is the width of the equipment definition. The order covers "items used in bulk-power system substations, control rooms, or power generating stations" and then lists them: reactors, capacitors, substation transformers, grid-connected inverters, battery energy storage systems, uninterruptible power supplies, circuit breakers, generators, protective relaying equipment, metering equipment, industrial control systems — remote terminal units, programmable logic controllers, intelligent electronic devices — distributed control systems and safety instrumented systems. It then extends to "associated software and firmware, remote access capabilities, lifecycle maintenance and update mechanisms, and other supply chain dependencies." That last clause is the one procurement lawyers will spend the autumn on, because a firmware update path is a supply-chain dependency that exists after the hardware is installed and paid for.

The second is that no country is named. A Covered Foreign Entity is defined by conduct: a government subject to US arms embargoes or sanctions regimes, or one engaged in conduct "detrimental to the national security or foreign policy of the United States." This is a category, not a list.

The third is the calendar. The Secretary of Energy has 120 days to publish implementing rules and 180 days to develop recommended Federal Acquisition Regulation revisions, and is separately directed to identify equipment already installed that poses a risk and to recommend responses including isolation, monitoring or removal. As of publication the order had not yet appeared in the Federal Register, whose most recent presidential documents were signed on 21 August.

The order at a glance, verified Detail
Signed Wednesday 26 August 2026
Title Declaring a National Emergency to Secure the United States Bulk-Power System
Authorities IEEPA (50 U.S.C. 1701 et seq.), National Emergencies Act (50 U.S.C. 1601 et seq.), 3 U.S.C. 301
Prohibits Acquisition, importation, transfer, installation of covered foreign-produced bulk-power equipment
Countries named None — "Covered Foreign Entity" defined by sanctions status and conduct
Dollar threshold None specified
DOE implementing rules due 120 days — 24 December 2026
FAR revision recommendations due 180 days — 22 February 2027
Installed equipment Secretary of Energy to identify risks; isolation, monitoring or removal
Only statistic in the White House fact sheet 17,000 MW of plants kept from going offline in April 2025, "enough electricity to supply power to 12.75 million homes"
Why IEEPA, six months after the Supreme Court cut it backOn 20 February 2026 the Court held 6-3 that IEEPA does not authorise the president to impose tariffs, because the tariff power is a branch of the taxing power reserved to Congress under Article I; all IEEPA-based tariffs terminated on 24 February 2026. It would be easy to read this order as testing that ruling. It is not. The Court's reasoning was about taxation, and a prohibition raises no revenue — blocking property and barring transactions is what IEEPA was written to do in 1977 and is the machinery behind every US sanctions programme in force today. So the statute now has one door closed and one open, and the two doors transmit to markets differently. A tariff is a price instrument: it raises landed cost, importers and consumers split it, and the volume adjusts second. A prohibition is a quantity instrument: the volume adjusts first, and the price of whatever remains adjusts to the shortage. In a category with 82% import dependence and multi-year lead times, the second is the more disruptive of the two even when the covered set is far smaller. This is the same sector-by-sector, statute-specific pattern traced in the September drone tariffs, which reached the same goal through Section 232 instead.

The number that decides how much this matters

Restricting a supply source matters in proportion to how fast the remaining sources substitute. On this equipment, they substitute very slowly, and the evidence is the government's own.

DOE's July 2024 Large Power Transformer Resilience report cites a Department of Commerce estimate that in 2019, 137 large power transformers — units rated 100 MVA or above — were produced domestically for domestic use while 617 were imported and four exported. That is 18% against 82%. The same survey put domestic capacity utilisation at roughly 40% and derived a maximum domestic capacity of about 343 units a year. DOE estimates 4,900 to 6,799 of these transformers are in service, that approximately 90% of all electricity consumed in the United States passes through at least one, and that more than 70% of them are already over 25 years old against a typical 40-year life. On lead times, the report is blunt: 36 months "commonly quoted", with maximum lead times "reaching as much as 60 months."

US large power transformers (100 MVA+), from DOE and Commerce Figure
Imported for domestic use, 2019 617 units — 82%
Produced domestically for domestic use, 2019 137 units — 18%
Domestic capacity utilisation ~40%
Maximum domestic capacity ~343 units/year
Units in service (DOE, 2022) 4,900 – 6,799
Share of US electricity passing through at least one ~90%
Share aged over 25 years more than 70%
Lead time commonly quoted 36 months (max ~60 months)

The constraint is one layer below the transformer

The part a headline cannot carry is that the domestic alternative is itself import-dependent. Grain-oriented electrical steel — the low-loss steel a transformer core is built from — and continuously transposed copper conductor each account for roughly 25% of final production cost, on a 2020 Commerce industry survey. Approximately 80% of that steel was imported in 2019, and DOE's breakdown by form is starker: 88% of pre-cut lamination sheets, 80% of pre-assembled stacked cores, and 100% of wound cores, which require the highest grade.

That highest grade is the sentence worth rereading. Permanent Domain-Refined grain-oriented electrical steel "is only available from a single manufacturer, Nippon Steel in Japan, and is not manufactured in the U.S." There is one American producer of grain-oriented electrical steel at all, and DOE records that it "has been unable to meet domestic demand at quality and prices comparable to imports" — while domestic demand for the non-oriented steel used in electric vehicle motors competes for the same mill capacity and crowds out the less profitable oriented product. Even the machines that make transformers are constrained: winding machines and core tables take one to two years to obtain.

None of that is a consequence of the new order. It is the terrain the order lands on, and it is why the distinction between a price instrument and a quantity instrument is not academic here.

Order signed26 Aug 2026 — category defined, scope blank
DOE ruledue 24 Dec 2026 — the covered set becomes real
Procurementre-sourcing, re-qualification, requeuing
Rate basecapex enters approved revenue requirement
Retail pricethen, eventually, the CPI electricity line

Why it landed as a policy event and not a price event

The order arrived in a week the equity market was occupied with semiconductor guidance, and it did not trade. That is the correct response rather than a market failure, and the reason is in the drafting: a category with no country attached and no rule yet written cannot be sized. An equipment maker cannot tell an investor what fraction of its bill of materials is covered, because "Covered Foreign Entity" has not been operationalised. A utility cannot tell a regulator what the order costs, because the answer arrives with the rulemaking. Industry response has accordingly been about definitional clarity rather than cost — Edison Electric Institute spokesperson Dani Marx said utilities "are committed to working with DOE on the implementation of [the] order to ensure that we can maintain the reliability and affordability of electricity", while the National Electrical Manufacturers Association's Bridget Bartol flagged the risk of market confusion, particularly on how software is defined.

There is precedent for how this can end, and it is worth holding as a reference case rather than a forecast. Executive Order 13920, signed 1 May 2020, made a narrower version of the same move, aimed squarely at large power transformers from foreign adversaries. It was suspended for 90 days on 20 January 2021, and the accompanying prohibition order was revoked on 20 April 2021 — before its operational rules had reshaped much procurement at all. An order of this kind is a delegation of authority. What it becomes depends entirely on the rule.

See how the rate, growth and risk factors are scoring the eight majors right now.Open the live meter →

The demand side, and why the timing is not incidental

A supply-chain rule on grid equipment is more consequential in 2026 than it would have been in 2016 because the grid is being asked to grow again. The IEA's Electricity 2026 forecasts global electricity demand rising at an average 3.6% a year through 2030, roughly 50% faster than the previous decade's average, with United States demand growing by nearly 2% a year and "around half of the total increase driven by the rapid expansion of data centres." The spending is already committed: Edison Electric Institute's capital expenditure series for US investor-owned utilities projects $1.1 trillion across 2025-2029 — $207.9bn in 2025 rising to $248.4bn in 2029 — against $1.3 trillion spent across the whole of 2015-2024. A decade of spending compressed into five years, and every dollar of it has to buy equipment from somewhere.

On concentration, the IEA's manufacturing work is the backdrop: China holds close to 85% of global battery cell production capacity, accounted for over 80% of total battery production in 2025, and exceeds 80% at every solar manufacturing stage. Batteries and grid-connected inverters are both named in the order's equipment list. The security rationale is documented rather than hypothetical — Reuters reported in May 2025 that undocumented communication devices, including cellular radios, had been found in Chinese-made inverters and batteries, providing undisclosed channels that could allow firewalls to be circumvented remotely. Al Jazeera's account of the order quotes John Bruggeman of CBTS on the harder half of the problem: "Blocking new purchases is the easy part. Knowing what's already running is where the real work starts."

The channel that reaches something you can trade

Be honest about the distance. This is not an FX story today, and forcing it into one would be worse than leaving it out. The connection that does exist runs through the price of electricity, and it is slow, mediated by regulators, and currently unquantifiable.

The chain is nonetheless real: utility capital spending enters the rate base, the rate base enters the approved revenue requirement, the revenue requirement enters retail tariffs, and retail tariffs enter the consumer price index. That line is already outrunning the index it sits in. On Bureau of Labor Statistics data, the electricity index for all US city consumers rose 4.20% in the twelve months to July 2026, against a 3.36% rise in headline CPI. Over two years the gap is wider: electricity up 9.97%, headline up 6.16%. Monthly readings have decelerated from April's 6.09% but remain above the aggregate.

For anyone reading the dollar off the inflation path — and the rate factor is one of the five the meter scores across the eight majors — the framing is that electricity is a persistent, supply-driven component monetary policy does not reach, and that a rule constraining equipment supply pushes on it in one direction only. What the rule cannot tell you is by how much. Set that against the disinflation already banked in the goods components in the July CPI breakdown, and against the same AI-power demand seen from the semiconductor side in silicon carbide. The live factor read for the dollar sits on the USD currency page, and the method behind it is set out in how this site works.

What would change the picture

The DOE rule, due 24 December 2026. This is the event. If the covered set is drawn narrowly — a short list of entities, a grace period for equipment already ordered, a clear software carve-out — the order is a compliance exercise. If it is drawn to the full width of the equipment definition, including firmware and remote maintenance paths, it reprices procurement across a $1.1 trillion capital programme.

The treatment of installed equipment. New purchases are the tractable half. A requirement to isolate, monitor or remove equipment already energised is a different order of cost, and it is the half the order leaves most open.

Whether the FAR revisions reach beyond federal procurement. The 22 February 2027 deadline covers government acquisition. Whether the same standards migrate into state regulatory practice determines whether this touches the investor-owned utilities that do the spending.

Reciprocity. The order restricts imports of equipment whose highest-grade inputs the United States does not make. Watch how supplying countries respond, particularly on the steel.

Until the first of those lands, the correct position is the one the market took: this is a rule about the future scope of a category, and a category is not yet a cost.

Educational macro context only — not investment advice.

Advertisement

Frequently asked

What does the 26 August 2026 bulk-power system executive order actually do?
It declares a national emergency and generally prohibits the acquisition, importation, transfer or installation of foreign-produced bulk-power system electric equipment in which a 'Covered Foreign Entity' has an interest, for transactions initiated after the date of the order. The equipment definition is unusually wide: reactors, capacitors, substation transformers, grid-connected inverters, battery energy storage systems, uninterruptible power supplies, circuit breakers, generators, protective relaying equipment, metering equipment, industrial control systems including remote terminal units, programmable logic controllers and intelligent electronic devices, distributed control systems and safety instrumented systems — plus, critically, the associated software and firmware, remote access capabilities, lifecycle maintenance and update mechanisms and other supply-chain dependencies. The order gives the Secretary of Energy 120 days to publish implementing rules and 180 days to develop recommended Federal Acquisition Regulation revisions, and directs him to identify equipment already installed that poses a risk, with options including isolation, monitoring or removal. Until the rules exist, nobody — including utilities — can say precisely which parts are covered.
Which countries does the order name?
None. The order does not name a single country. Instead it defines a 'Covered Foreign Entity' functionally: a country or a person owned or controlled by a government that is subject to US arms embargoes or sanctions regimes, or that engages in conduct detrimental to the national security or foreign policy of the United States. That drafting choice is the whole reason the market cannot size the order yet. A rule that names three countries and four tariff lines can be priced in an afternoon; a rule that describes a category of conduct and hands the definition to an agency cannot be priced until the agency writes it down. The implementing rules are due within 120 days of signing, which falls on 24 December 2026.
Is this the same as the tariffs the Supreme Court struck down in February 2026?
No, and the distinction is the point. On 20 February 2026 the Supreme Court held 6-3 that the International Emergency Economic Powers Act does not authorise the president to impose tariffs, reasoning that the tariff power is a branch of the taxing power reserved to Congress under Article I. This order is built on the same statute — but it does not tax anything. It prohibits transactions, which is the function IEEPA has performed since 1977 and the function the Court's reasoning left entirely intact: blocking, embargoes and sanctions are not exercises of the taxing power. So the February ruling closed one door in the statute and left the other one open, and this order walks through the open one. The market consequence differs accordingly. A tariff raises a landed price and the market clears at the higher price; a prohibition removes a source of supply and the market clears through a queue.
Why does the 82% import figure matter so much here?
Because it measures how little slack the domestic alternative has. A 2019 Department of Commerce estimate cited in the Department of Energy's July 2024 Large Power Transformer Resilience report found that 137 large power transformers — units rated at 100 MVA or above — were produced domestically for domestic use, against 617 imported: 18% versus 82%. The same survey put domestic capacity utilisation at roughly 40% and maximum domestic capacity at about 343 units a year. DOE separately estimates 4,900 to 6,799 large power transformers are in service in the United States, that roughly 90% of all electricity consumed in the country passes through at least one of them, and that more than 70% of them are over 25 years old. Restricting a supply source matters in proportion to how quickly the remaining sources can substitute, and on DOE's own figures the remaining domestic source is small, already the expensive option, and constrained by inputs it does not make.
How could a grid equipment rule reach inflation data?
Through the electricity line of the consumer price index, on a long lag and only if the rule raises equipment costs or extends delivery queues. Utility capital spending enters the rate base, the rate base enters approved retail rates, and retail rates enter the CPI. That line is already running hot: on Bureau of Labor Statistics data, the electricity index for all US city consumers rose 4.20% in the year to July 2026 against a headline CPI increase of 3.36%, and over two years electricity is up 9.97% against 6.16% for headline. This is a slow channel measured in regulatory quarters, not a trade that exists today — and the honest statement is that the sign is knowable while the size is not, because the size depends on a rule that has not been written.
PT
Pip Theory desk

We build the tools we write about. Educational macro context only — never investment advice.

About the desk